US Green Building Council LEED-AP-ID+C LEED AP Interior Design + Construction V4 Exam Practice Test

Page: 1 / 14
Total 100 questions
Question 1

In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?



Question 2

The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will



Question 3

A project owner requests that additional outside air be provided to the building occupants in order to improve employee health, welfare, well-being and productivity. However, doing so could make it more difficult to achieve which credit?



Question 4

A tenant moves into an existing building where no modifications to the building envelope will be made. What credit would be affected by the visible light transmittance of the existing exterior glazing?



Question 5

Which of the following can be considered pre-consumer recycled content?



Answer : C

Pre-consumer recycled content refers to materials that have been diverted from the waste stream during the manufacturing process but have not yet been used by a consumer. Sawdust from a lumber mill, which is used to make composite board, is an example of pre-consumer recycled content because it is a by-product of the manufacturing process that is being repurposed into a new product.


Question 6

Based on the results of a six-hour waste stream study, the team for an Interior Design and Construction Retail project plans to provide dedicated areas for four recyclable waste streams: cardboard, plastic, metal, and paper.

The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?



Answer : D

For the Materials and Resources Prerequisite, Storage and Collection of Recyclables, the project team must demonstrate that they can effectively manage and divert waste from landfills. Extending the waste stream study to a minimum of 24 hours will provide a more accurate representation of the waste generated and the recyclable streams. This is essential to identify the top five recyclable waste streams, which is a requirement for this prerequisite.


Question 7

Which systems must be commissioned to earn Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?



Answer : C

The Fundamental Commissioning and Verification prerequisite requires commissioning of the building's mechanical, electrical, plumbing, and renewable energy systems and assemblies. While the building envelope is not typically commissioned, it must be included in the owner's project requirements (OPR) and basis of design (BOD), and its design must be reviewed.


Page:    1 / 14   
Total 100 questions