Question 1

When does the product owner accept or reject the user stories included in the Sprint?



Answer : A


Question 2

What are key goals of the burndown chart? Note: There are 2 correct answers to this question.



Answer : C, D


Question 3

In which phase of SAP Activate does the SAP Project Manager set up project governance?



Answer : A


Question 4

What is an activity that is performed at the end of the Realize phase?



Answer : C


Question 5

In which phase do you create "an ordered list of everything that is known to be needed in the product"?



Answer : D


Question 6

What is the key difference between Notes and Requirements in the Change and Deploy capability of SAP Cloud ALM?



Answer : C


Question 7

What are potential use cases for SAP Cloud ALM? Note: There are 2 correct answers to this question.



Answer : A, B