For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.
Answer : A, B, C
Which master data object governs the relationship between supply source and demand source in the Kanban process?
Answer : C
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
Answer : C, D
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
Answer : B, D, E
What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?
Note: There are 2 correct answers to this question.
Answer : A, B
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?
Note: There are 2 correct answers to this question.
Answer : B, C
You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?
Answer : B