SAP C_TS422_2021 SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Page: 1 / 14
Total 82 questions
Question 1

Which of the following elements does MRP take into account during net requirement calculation?



Answer : B, D


Question 2

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?



Answer : A, D


Question 3

Which of the following processes lead to an entry in the MRP planing file?



Answer : A, C, D


Question 4

What is the purpose of a reporting point confirmation in repetitive manufacturing?



Answer : B, D


Question 5

Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?



Answer : A, C, D


Question 6

How can you carry out cost object controlling for production orders?



Answer : C, D


Question 7

Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?



Answer : A, C


Page:    1 / 14   
Total 82 questions