Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question
Answer : B, C
Which of the project definition in project management must be filled before you can release a project?
Answer : C
You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS?
NOTE: There are 3 correct answers to this question
Answer : A, B, C
What is the PR/PLAN_INI_PREP report used for?
Answer : A
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?
Answer : B, C, E
What are dashboard alerts calculations based on?
Answer : B
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
Answer : C