PRINCE2-Agile-Foundation PRINCE2 Agile Foundation Exam Practice Test

Page: 1 / 14
Total 92 questions
Question 1

Which TWO statements about the supplier subject matter expert are CORRECT?

1) They provide a wider picture of the customer view.

2) They prioritize requirements at the detailed level.

3) They should be focused on the customer.

4) They ensure that the work is compliant with project standards.



Answer : C


Question 2

Which should be an objective of a retrospective?



Answer : B


Question 3

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?



Answer : A


Question 4

Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?



Answer : C


Question 5

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?



Answer : B


Question 6

How does agile address the risk associated with the project not being fully understood at the beginning?



Answer : D


Question 7

Which is typically used in agile when estimating detailed requirements during sprint planning?



Answer : A


Page:    1 / 14   
Total 92 questions