The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual
products being worked on.
Which part of effective issue management is the project manager applying?
Answer : A
In PRINCE2, baselines are used to establish a reference point for the agreed state of products, against which actual progress can be compared and managed. By requesting a report to check for conflicts between the agreed and actual states of products, the project manager is effectively applying the concept of baselines within issue management. This helps in identifying deviations from the agreed deliverables and initiating corrective actions to address these discrepancies. Reference: (PRINCE2 7 Foundation Handbook, AXELOS)
Which describes user's quality expectations?
Answer : A
User's quality expectations are documented in the 'Project Product Description.' This document defines what the project must deliver to meet the user's expectations, including the quality requirements and acceptance criteria for the final product, ensuring alignment with user needs and standards. Reference: PRINCE2 7 Foundation documentation on quality management and project product descriptions.
What does qualitative analysis of a risk assess, as a minimum?
Answer : C
Qualitative analysis of a risk in PRINCE2 assesses, at a minimum, the likelihood of each risk occurring and its potential impact on project objectives. This analysis helps in prioritizing risks based on their severity and likelihood, which is crucial for effective risk management and decision-making about risk responses. Reference: (PRINCE2 7 Foundation Handbook, AXELOS)
Which should provide guidance on how and when prototyping is to be used?
Answer : B
The Quality Management Approach in PRINCE2 should provide guidance on how and when prototyping is to be used within the project. This approach outlines the quality techniques and standards to be applied and the responsibilities for achieving the required quality levels. Prototyping, as a method to validate product quality and user requirements early in the development cycle, falls under these guidelines. Reference: (PRINCE2 7 Foundation Handbook, AXELOS)
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Answer : D
In PRINCE2, the project baseline should be updated when a change has been formally approved by the change authority. This is because the baseline represents the agreed standards and plan against which the project's performance is measured. Updating the baseline after the approval of changes ensures that the project documentation accurately reflects the current scope, timescales, and resource allocations, which are essential for tracking progress and managing by exception effectively. Reference: (PRINCE2 7 Foundation Handbook, AXELOS)
Which role is responsible for focusing on the safety and well-being of the project team?
Answer : D
In the PRINCE2 framework, the team manager is the role primarily responsible for the welfare, including the safety and well-being, of the project team. This role involves managing the team environment and ensuring that team members are supported throughout the project's lifecycle. Reference: PRINCE2 7 Foundation guide and resources detailing project roles and responsibilities.
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
Answer : A
In PRINCE2, an 'outcome' is defined as the result achieved by the project after implementing changes through its activities. Outcomes are the new states enabled by the project's outputs, differing from benefits in that they are not necessarily quantified as improvements until later evaluated as such. Reference: PRINCE2 7 Foundation documentation on project outputs, outcomes, and benefits.