You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?
Answer : D
According to the question, you have to use the estimating technique that has a higher
degree of accuracy. The most accurate estimating
technique is bottom-up estimating.
What is bottom-up estimating?
Bottom-up is a cost estimating technique that involves estimating the cost of individual work
packages or schedule
activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher
levels for total project
estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up
estimating provides a
higher degree of accuracy, provided the estimates at the work package level are accurate.
Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques
use top-down estimation model. These
are less accurate than the bottom-up estimation.
What is analogous estimating?
Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget,
and duration or
measures of scale such as size, weight, and complexity from a previous, similar activity as the basis
for estimation of the
same parameter for a future activity. It is a top-down estimating technique and is a form of expert
judgment. It provides a
lower degree of accuracy than other estimating techniques. This technique is primarily used when
there is a limited amount
of detailed information about the project or program.
What is parametric modeling?
Parametric modeling is an estimating technique that uses parameters, or project characteristics, to
forecast project costs.
It involves a top-down approach and is similar but more accurate than analogous estimating. It uses
historical data and
other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and
duration.
Which of the following provides a method to track project progress during project execution against what was planned?
Answer : C
A schedule baseline provides a method to track project progress during project
execution against what was planned.
What is schedule baseline?
Schedule baseline is a project schedule used in measuring project progress. It helps provide a
comparison with the actual
progress of work against the schedule and to determine if performance to date is within acceptable
parameters. Any
change caused by change in scope of the project invalidates the original schedule and requires a new
baseline schedule.
Answer options D, A, and B are incorrect. A detailed project budget, team members profile, and
benefit-cost ratio will not help you track
project progress.
What is BCR?
A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that
attempts to summarize
the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or
proposal, expressed in
monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should
be expressed in
discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar
expended.
Which of the following is NOT an output of the control schedule process?
Answer : C
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.
Answer : A, B, D
A scheduler schedules the constraints for the project into phases with respect to the
time and resources available. He can be hired from
outside a company, or from within a company. The basic roles of a scheduler are as follows:
Feasibility Planning: A scheduler is the time management expert who paints a picture of the project.
He develops a strategy for
delivery and to gain consensus.
Execution Schedule: A scheduler works with the project team to optimize and refine the schedule
until an agreed schedule has been
developed.
Performance Control: A schedule is maintained by the scheduler who optimizes outcomes and
instructs the project team on their
presentation. It is important that the scheduler be aware of the changes and trends related to the
project delivery.
Answer option C is incorrect. This is the skill possessed by the project manager.
You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by July 2. With the current resources you have and the resource leveling imposed, you would not be able to finish by the constraint. What document should you update to address this situation?
Answer : A
The activity resource requirements will need to be addressed because the imposed
constraint will cause a need for more resource to complete
the activities by July 2.
What is resource leveling heuristics?
Resource leveling heuristics is a prioritization method that allocates inadequate resources to critical
path activities first. It is
a schedule network analysis technique useful to a schedule that has already been analyzed by the
critical path method. It
is used when shared or critical essential resources are only available at certain times, in limited
quantities, or to keep
resource usage at a constant level. It is a technique that resolves resource conflicts by delaying tasks
within their slack
allowances. Resource leveling is the process in which project teams come across problems when
developing their project
schedules. If a company has multiple projects running simultaneously that require the same
resources, then problems can
arise. It can often cause the critical path method to change.
Answer option C is incorrect. The project scope does not need to be addressed as there has not been
a request to reduce or increase the
project scope.
Answer option B is incorrect. The project charter will not change. In fact, the charter will rarely, if
ever, change once has been approved and
signed.
Answer option D is incorrect. The schedule management plan would not be the biggest concern in
this instance. The plan defines how the
schedule will be created, executed, monitored and controlled.
You are the project manager for the NHQ project. The management has reminded you that you must
not allocate any project team member for more than 25 hours per work week on your project. This
policy is because your organization is in a weak matrix and the project team members are on several
projects at once within the organization. The 25-hour limit per resource is an example of which one
of the following?
Answer : B
The limit on each work is an organizational policy for each project. Policies, rules, and
organizational requirements are the enterprise
environmental factors.
Answer option D is incorrect. Organizational process assets are things that have been created for the
project manager, such as software,
templates, guidelines, and other resources that will assist the project manager in completing the
project.
Answer option C is incorrect. While this could be a resource limitation, it is not a valid project
management term. Resource leveling heuristics
or a project constraint would have been acceptable answers.
Answer option A is incorrect. Expert judgment happens, when the project manager relies on
someone with more knowledge on a topic to help
the project manager make the best project decision.
You are the project manager for your organization. Your current project has a schedule variance of -
$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project
performance?
Answer : D
A schedule variance is found by subtracting the planned value from the earned value. A
-$37,500 schedule variance is considerable for most
projects, but combined with a schedule that is six percent off schedule is more serious. The size of
the project, however, and the defined
project budget, needs to be determined to evaluate how serious the variance is.
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that
the schedule is ahead or behind what
was planned for this period in time. The schedule variance is calculated based on the following
formula:
SV = Earned Value (EV) - Planned Value (PV)
If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater
than 0 shows that the project is ahead of
the planned schedule. A value of 0 indicates that the project is right on target.
Answer option B is incorrect. This project is not performing well based on the given information.
Answer option A is incorrect. This project is likely to be late, but we do not know how costs are
performing in this question.
Answer option C is incorrect. There is not enough information to determine how well the project is
performing from this answer.