with the appropriate word. When activities are logically linked, they become the .
__________
See Below Explanation:
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Answer : A
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?
Answer : D
This is an example of corrective action. The project team will fix the mistake and they
have learned from their mistake so it won't happen again.
Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce
the probability and impact of an identified
risk event.
Answer option A is incorrect. A risk response is an action to counteract an identified risk.
Answer option B is incorrect. There may be some team development happening in this instance but
we don't have enough information to know
for certain. Team development is an activity that brings the whole team cohesion, interdependency,
and trust.
You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee of this company wants to know what are the inputs for generating performance reports. Which of the following are the necessary inputs? Each correct answer represents a part of the solution. Choose two.
Answer : B, C
According to the scenario, you can use the following inputs in order to generate
performance reports:
WPI: Work performance information is the data gathered on the status of the project schedule
activities that are performed to
accomplish the project work. This data is collected as part of the Direct and Manage Project
Execution processes. WPI includes the
following:
Deliverables status
Schedule Progress
Costs incurred
WPM: Work performance measurements are created from the work performance information.
WPMs are an output of Control schedule,
Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs
consist of planned versus actual
performance indicators with respect to scope, schedule, and cost. They are documented and
communicated to the stakeholders and are
used to make project activity metrics, such as the following:
Planned vs. Actual Technical performance and Scope performance
Planned vs. Actual Schedule performance
Planned vs. Actual Cost performance
Answer option A is incorrect. Variance analysis is an after-look at what caused a difference between
the baseline and the actual performance.
It is one of the tools and techniques used for report performance.
Answer option D is incorrect. Change requests are requests to expand or reduce the project scope,
modify policies, processes, plans, or
procedures, modify costs or budgets or revise schedules. These requests for a change can be direct
or indirect, externally or internally
initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that
only formally documented requested
changes are processed and only approved change requests are implemented.
Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?
Answer : B
Fred should add lag time to each painting activity. Since lag time is waiting time, Fred
will have to wait twenty-four hours after the priming is
finished before he can start painting.
What is a lag?
A lag directs a delay in the successor activity. Lags require the dependent activity to have added
either to the start date or
to the finish date of the activity. For example, in a project of making radio-controlled airplanes, after
applying glue and
pasting stickers, it requires twenty-four hours to dry the glue. Any activity can be started after that
only. This period, of
twenty-four hours, is a lag.
Answer option C is incorrect. There is no reason to add an intermediary task as waiting. Adding lag
time is the most appropriate as there are
fewer activities to manage.
Answer option D is incorrect. Priming all of the room first and then painting all of the rooms would
cause Fred to readjust the entire
sequencing of activities. In addition, we do not know the reason why Fred has scheduled all the
rooms to be primed and then painted. There
may be successor activities in the project that need to enter each room, such as carpeting, as soon
as a room has been painted. If that were
the case the additional activities would have to wait for all of the priming to be completed and then
the sequential rooms to be painted before
they could start.
Answer option A is incorrect. Lead time actually moves activities closer together rather than farther
apart. Lead time would cause the painting
and priming activities to overlap, something that Fred does not want to happen.
What is a lead?
A lead allows an acceleration of the successor activity. It works just the opposite of lag. For example,
in a software
application project, before designing is fully completed for first phase, a program development
group can start this phase
programming. This overlapping of timing is a lead.
Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: Measurements Values BCWP (or EV)425 BCWS (or PV) 400 ACWP (or AC)510 What is the schedule performance index (SPI) of the project at the current point of time?
Answer : C
According to the question, you are required to calculate the schedule performance
index (SPI) of the project. Schedule performance index
(SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future
performance. SPI is the ratio of earned
value to planned value. The SPI is calculated based on the following formula:
SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value
is less than 1, it shows poor
performance. The SPI value of 1 indicates that the project is right on target. Here, SPI is calculated as
follows:
SPI = EV / PV
= 425/400
= 1.0625
As the SPI (1.0625) is greater than 1, it shows that the schedule performance is better than
expected.
What is BCWP (or EV)?
Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is
the budgeted amount
for the work actually completed on the schedule activity during a given time period.
What is BCWS (or PV)?
Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned
to the scheduled work
to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.
What is ACWP (or AC)?
Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and
recorded in accomplishing
work performed during a given time period for a schedule activity. It is the cost of the work to date,
including direct and
indirect costs. AC is money that has actually been expended to date.
You work as a stakeholder for ABC Inc. You are on an important feature of a project that appears too
difficult to execute. Issues like acceptable type of bugs and number of bugs for user acceptance
seem to have affected the project. What is the rate of risk factor in such a situation?
Answer : A
This happens when most of the stakeholders are concerned about risks.
Risk factors are determined for the scope of the project, requirements, design and strategy,
technology, processes (for development,
payment, change management, risk management, and closing the project), and conditions of the
project.
Risk factors are high when most of the stakeholders have concerns. Even if one important feature of
a project appears too difficult to execute,
the risk is high. Issues like acceptable type of bugs and number of bugs for user acceptance, terms
for closing the project, payments not being
clear or misunderstood, make the project highly risky.
Answer option B is incorrect. Risks are low when issues like the format of the forms are not finalized
but the functionality is thoroughly
understood and solutions are approved.
Answer option D is incorrect. Risks are rated medium when a very small number of stakeholders
have a few concerns. For example, the
development team may not have very advanced knowledge of the technology but could provide
some work around. Another could be that the
customer's people cannot finalize a few unimportant workflows.
Answer option C is incorrect. It is an invalid answer.
You are the project manager for your organization. You are coaching Allen, a junior project manager,
on how the details of the project's critical path are calculated. Examine the figure given below:
What is the critical path of this project?
Answer : B
The critical path is discovered by summing the duration of each activity node in each
chain of activities in the project network diagram. In this
figure, the critical path is ACFGJ, which is 26 days, the longest chain of activities in the project.
Answer option A is incorrect. This path's duration is 22 days.
Answer option D is incorrect. This path's duration is 23 days.
Answer option C is incorrect. This path's duration is 15 days.