An external vendor is assigned a project task in response to a capacity and expertise risk. The project team is concerned about the vendor's engineers' ability to communicate properly in the local language
What should the risk manager do in this case?
Answer : B
A team of experts is working on a complex project. Which three tools could support the risk manager in discovering the overall project risk complexity? (Choose 3)
Answer : B, C
A key hardware component failed during a large software implementation project with significant organizational impact. The risk owner was on vacation and no one responded to this incident thereby causing project delays.
What should have been done to prevent this situation?
Answer : D
Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?
Answer : B
When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?
Answer : C
A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information such as scope baseline and project estimates while also determining risk impacts based on this approach.
Which risk identification approach should the risk manager use to achieve this goal?
Answer : B
A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?
Answer : D