PMI Program Management Professional PMI-PgMP Exam Practice Test

Page: 1 / 14
Total 453 questions
Question 1

A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program.

Would this be an acceptable funding arrangement?



Answer : A


Question 2

A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility.

What other important step should the program manager complete?



Answer : A


Question 3

When should a program manager approve the closure of a component project?



Answer : C


Question 4

A company hires a program manager to create a healthcare management system. After five months, the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?



Answer : B


Question 5

A company is rolling out an innovative program that includes new processes intended to define how the company will manage future programs. While program execution is going well, the program sponsor is concerned that the knowledge acquired needs to be reused for future programs.

What should the program manager do to ensure that the knowledge acquired is captured efficiently?



Answer : A


Question 6

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively

address the risks.

In this situation, what should the program manager change about the risk management plan?



Answer : A


Question 7

A component is scheduled to close at the end of the week.

What should the program manager verify prior to allowing the component to close?



Answer : B


Page:    1 / 14   
Total 453 questions