PMI Program Management Professional PMI-PgMP Exam Practice Test

Page: 1 / 14
Total 453 questions
Question 1

A program is in its last year of execution. The program manager will receive a performance bonus if executive leadership and the program steering committee determine that the program is a success.

How can the program manager justify receiving a performance bonus upon program closure?



Answer : C


Question 2

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?



Answer : C


Question 3

An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.

What should the program manager do first to obtain program approval?



Answer : A


Question 4

A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?



Answer : A


Question 5

The program manager leads a medical billing system integration program for company A, a health services provider. Company A acquires smaller company X, which delivers health services strategically aligned with company A.

Company X uses a different billing approach than company



Answer : A, A


Question 6

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?



Answer : B, C


Question 7

A software company's program manager is conducting closing procedures for a program. At the last steering

committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?



Answer : A


Page:    1 / 14   
Total 453 questions