PMI PgMP Program Management Professional PMI-PgMP Exam Practice Test

Page: 1 / 14
Total 453 questions
Question 1

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?



Answer : C


Question 2

A software company's program manager is conducting closing procedures for a program. At the last steering

committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?



Answer : A


Question 3

A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.

What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?



Answer : D


Question 4

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?



Answer : B


Question 5

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?



Answer : A


Question 6

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively

address the risks.

In this situation, what should the program manager change about the risk management plan?



Answer : A


Question 7

A component is scheduled to close at the end of the week.

What should the program manager verify prior to allowing the component to close?



Answer : B


Page:    1 / 14   
Total 453 questions