PMI CAPM Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

What is the primary benefit of the Manage Quality process?



Answer : B


Question 2

What specific quality considerations should be examined while completing Quality Management plan?



Answer : C


Question 3

What is an example of an emerging trend in procurement management?



Answer : D


Question 4

What key component of the project charter defines the conditions for dosing a project phase?



Answer : C


Question 5

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?



Answer : A


Question 6

Select three processes that are associated with Project Schedule Management.



Answer : A, C, D


Question 7

Select two key benefits of the Control Procurements process



Answer : B, D


Page:    1 / 14   
Total 1135 questions