PMI CAPM Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

What characteristic of servant leadership supports resource management in an agile environment?



Answer : D


Question 2

What process is included in Project Integration Management?



Answer : A


Question 3

What does earned value (EV) measure?



Answer : A


Question 4

During what project management process does the project team begin identifying risks?



Answer : B


Question 5

What internal enterprise environmental factor (EEF) can impact a project?



Answer : D


Question 6

What benefit does the Manage Stakeholder Engagement process offer?



Answer : B


Question 7

What is the Project Schedule Management practice used to deliver incremental value to the customer'?



Answer : B


Page:    1 / 14   
Total 1135 questions