PMI CAPM Certified Associate in Project Management PMI CAPM Exam Practice Test

Page: 1 / 14
Total 1135 questions
Question 1

What organizational process asset (OPA) might impact a project's outcome?



Answer : A


Question 2

What tool or technique will establish expected behaviors for project team members?



Answer : A


Question 3

What is the primary purpose of Project Scope Management?



Answer : C


Question 4

A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?



Answer : C


Question 5

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?



Answer : A


Question 6

For what project management process is work performance information an output?



Answer : A


Question 7

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?



Answer : B


Page:    1 / 14   
Total 1135 questions