NFPA Certified Fire Plan Examiner CFPE Exam Practice Test

Page: 1 / 14
Total 100 questions
Question 1

Which one of the following is a right given to a board of appeals?



Answer : D

The board of appeals does not have the authority to waive code requirements, set jurisdiction precedent, or withdraw a project. However, according to NFPA 1031, the board of appeals is typically granted the right to consider alternative methods or materials to those required by code, provided that they achieve the same level of safety. This is done to allow flexibility in the application of the code while maintaining safety and compliance.

The exact provisions for the board of appeals can be found in NFPA 1031 and the relevant local building and fire codes.


Question 2

In positive alarm sequence systems trained personnel shall have a maximum of how many seconds during the alarm investigation phase to evaluate the fire condition and reset the system'?



Answer : C

According to NFPA 72, National Fire Alarm and Signaling Code, in positive alarm sequence systems, trained personnel have a maximum of 120 seconds (2 minutes) during the alarm investigation phase to evaluate the fire condition and reset the system. This time frame is provided to allow personnel to assess whether the alarm is legitimate or false before activating a full evacuation or emergency response.

Top of Form

Bottom of Form


Question 3

Exhibit.

What is the construction type specified for the new addition for plan set Tl?



Answer : B

The construction type specified for the new addition in plan set T1 is Type II (000). This construction type, as defined in the International Building Code (IBC), refers to buildings with non-combustible materials for all structural elements, but with no fire-resistance rating requirements for any of the structural components. This is typical for newer additions where fire safety is achieved through non-combustible materials and other fire protection systems, such as sprinklers.

Top of Form

Bottom of Form


Question 4

For the purposes of fire sprinkler protection, occupancies where combustibility is low. quantity of combustibles is moderate, and stockpiles of combustibles do not exceed 8 ft (2.4 m). are called



Answer : B

Occupancies where the combustibility is low, the quantity of combustibles is moderate, and stockpiles of combustibles do not exceed 8 feet (2.4 meters) are classified as 'Ordinary hazard (Group 1).' This classification, as defined in NFPA 13, Standard for the Installation of Sprinkler Systems, is used to determine the design density and spacing of sprinklers required to provide adequate fire protection.


Question 5

Exhibit.

On plan A12 what occupant load factor would you use?



Answer : A

On plan A12, the occupant load factor to use is 30 ft (2.8 m) per person. This factor is used to calculate the maximum number of occupants for a given space based on its size and usage, ensuring that the building adheres to safe occupancy levels as required by fire safety codes. The occupant load factor is determined by the type of occupancy and activity level within the space and is outlined in NFPA 101, Life Safety Code, which provides guidelines for calculating occupant loads to ensure safety during an emergency evacuation.

Top of Form

Bottom of Form


Question 6

Which one of the following is an architectural drawing that shows the vertical view of a building, including floors, building height, and the grade of surrounding ground?



Answer : D

An elevation view is an architectural drawing that shows the vertical view of a building, including floors, building height, and the grade of surrounding ground. It is used to depict the exterior or interior walls of a structure from a vertical perspective. This view provides details on the heights of various building elements and their relationships to the surrounding terrain.


Question 7

What is a plans review checklist used for?



Answer : D

A plans review checklist is an internal guide used by plans examiners to ensure they do not overlook critical design aspects during the review process. It helps standardize the review procedure, making sure all essential code requirements and safety measures are considered before approving a plan. This tool is crucial in maintaining consistency and thoroughness in the plan review process.


Page:    1 / 14   
Total 100 questions