Microsoft MB-335 Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Exam Practice Test

Page: 1 / 14
Total 152 questions
Question 1

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen

A client subcontracts production work to a vendor for production operations.

You need to model subcontracting of route operations in production orders.

Solution: Ensure that the service product is stocked and is part of the Bill of Materials.

Does the solution meet the goal?



Answer : A


Question 2

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.

Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when the break starts.

You need to configure the break times to charge against the job in progress.

Which two actions should you perform? Each answer presents a partial solution.

NOTE; Each correct selection is worth one point.



Answer : A, D


Question 3

A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.

You need to optimize the planned production orders.

What should you do?



Answer : C


Question 4

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.

The company requires that employees register time against each machine on the shop floor.

You need to configure the system so that employees can register time.

Which two configurations must be set up? Each answer represents a partial solution

NOTE Each correct selection is worth one point.



Answer : A, B


Question 5

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.

The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.

You need to configure the system to meet the requirements.

Which three options should you configure? Each answer presents a partial solution.

NOTE: Each correct selection is worth one point.



Answer : B, D, E


Question 6

A co uses the asset management module in Supply Cham Management. The company has four conveyer systems in the warehouse. A robotic crane moves pallets of products to its conveyer int. Each robotic crane and conveyer line is considered a multilevel asset.

A work order arrives for a conveyer system. A technician completing the work observes that the robotic crane needs a repair. The technician is not qualified to work on the robotic crane.

You need to ensure that the robotic is repaired.

Which two options should you configure? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.



Answer : B, D


Question 7

You are the lead product design engineer at a plastics manufacturing company.

You implement a new process that uses a single to produce three finished at the same time.

You need to set up the planning items number and formula to correctly to manufacturing the tree items.

Which three actions should you perform? Each correct answer presents part of the solution.



Answer : A, B, C


Page:    1 / 14   
Total 152 questions