A company produces energy-efficient LED lighting solutions. Production is dependent on primary and secondary resources.
The primary resource is skilled assembly workers responsible for assembling LED lighting fixtures. The workers can work on only one fixture at a time during production.
The secondary resource is automated LED soldering machines, which typically operate at a 50% load capacity. The machines can work on multiple LED lighting fixtures at the same time.
The company must optimize the allocation of resources to meet customer demands efficiently.
You need to configure the resources to meet the customer demand.
What should you do?
Answer : C
A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
Purchase orders for a raw material are created more frequently than needed. This results in missed discounts with the vendor who sells the raw material.
The raw material items have a 30-day lead time. The company is willing to delay sales and production order demand that may consume the raw material for up to 15 days to consolidate purchase orders.
You need to configure the setup to include lead time and consolidate purchase orders.
What should you configure?
Answer : C
A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.
When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process.
You need to configure the functionality for the records.
At which two locations should you configure this functionality? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Answer : C, E
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear on the review screen.
A manufacturing company produces electronic components and devices.
The company has scheduling issues related to using working time calendars in manufacturing.
You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.
Solution: Enable route groups for a capacity job type.
Does the solution meet the goal?
Answer : B
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen
A client subcontracts production work to a vendor for production operations.
You need to model subcontracting of route operations in production orders.
Solution: Ensure that the material routing process is independent of the services procurement process.
Does the solution meet the goal?
Answer : B
A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
Answer : B, D, E
You need to set up the correct production solution for the assembly are
a. Which solution should you implement?
Answer : D