ISTQB ATM Advanced Test Manager Exam Practice Test

Page: 1 / 14
Total 64 questions
Question 1

A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase. Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas. Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?

K3 3 credits



Answer : B


Question 2

You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.

At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.

Which of the following statements is true in this context?

K4 3 credits



Answer : B


Question 3

Which of the following answers describes a factor that may reduce the effort spent when using distributed test teams without negatively affecting system quality?

K2 1 credit



Answer : D


Question 4

Assume you have some data related to confirmation testing during system testing of a past project.

In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.

You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 personhours.

Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?

K3 2 credits



Answer : A


Question 5

For which of the following activities would the costs be classified as a cost of detection? K2 1 credit



Answer : A


Question 6

In the test strategy document your organization declares:

- To adopt a V-model development lifecycle, with three formal levels of testing. unit, integration and system testing

- To use a blended risk-based and regression-averse testing strategy for each level of testing The following is an excerpt of the ''approach'' section for the system test plan document of a new project:

''Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.

Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected).'' In the system test plan, no deviations from the test strategy are described. Based only on the given information, which of the following statements is true?

K4 3 credits



Answer : D


Question 7

Assume you are currently working on a project developing a system where functional

requirements are very well specified. Unfortunately non-functional requirements do almost not exist.

You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.

Which of the following techniques for test selection do you expect being most useful in this scenario?

K2 1 credit



Answer : A


Page:    1 / 14   
Total 64 questions