iSQI CTAL-TM_Syll2012 ISTQB Certified Tester Advanced Level - Test Manager ISTQB® Exam Practice Test

Page: 1 / 14
Total 64 questions
Question 1

Assume you are managing a test automation project for a mission-critical system. Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework. Which of the following management issues associated to the development of this custom automation framework is least likely to manage?

K2 1 credit



Answer : C


Question 2

During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a ''new'' state, indicating it needs to be investigated.

Which THREE of the following information items can't yet be present in the incident report? K3 2 credits (2 credits out of 3 credits correct, 1 credit point)



Answer : A, C, D


Question 3

Which of the following statements best describes an appropriate approach for managing exploratory testing?

Number of correct responses: 1

K2 1 credit



Answer : B


Question 4

Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.

To which of the following activities would you expect the tester will contribute most?

K2 1 credit



Answer : D


Question 5

Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct? K2 1 credit



Answer : D


Question 6

In the test strategy document your organization declares:

- To adopt a V-model development lifecycle, with three formal levels of testing. unit, integration and system testing

- To use a blended risk-based and regression-averse testing strategy for each level of testing The following is an excerpt of the ''approach'' section for the system test plan document of a new project:

''Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.

Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected).'' In the system test plan, no deviations from the test strategy are described. Based only on the given information, which of the following statements is true?

K4 3 credits



Answer : D


Question 7

Assume you are currently working on a project developing a system where functional

requirements are very well specified. Unfortunately non-functional requirements do almost not exist.

You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.

Which of the following techniques for test selection do you expect being most useful in this scenario?

K2 1 credit



Answer : A


Page:    1 / 14   
Total 64 questions