GAQM PPM-001 Professional in Project Management (PPM) - Standard Package PPM Exam Practice Test

Page: 1 / 14
Total 650 questions
Question 1

Which tool or technique is used in Close Procurements?



Answer : D


Question 2

Which of the following is a schedule network analysis technique that takes limited resources into account?



Answer : B


Question 3

Which of the following is the correct network diagram for the table?



Answer : A


Question 4

What is the total float of the critical path?



Answer : C


Question 5

Which is a tool or technique used in scope definition?



Answer : C


Question 6

What is a hierarchically organized depiction of the identified project risks arranged by risk category?



Answer : B


Question 7

The initial development of a Project Scope Management plan uses which technique?



Answer : C


Page:    1 / 14   
Total 650 questions