The reported Cpk for a process with an average of 94 units, a spread of 22 units and upper and lower specification limits of 125 and 80 units would be?
Answer : B
The ____________ is important because it provides an estimate of the probability of an event occurring depending on the Standard Deviation from the Mean.
Answer : D
When constructing a Fishbone Diagram using the ________ approach is the most classic arrangement.
Answer : A
When looking at a distribution graph, the Mean is defined as the __________.
Answer : A
Nominal Scale data consists of names, labels or categories and cannot be arranged in any mathematical ordering scheme. Complex arithmetic functions cannot be easily applied to Nominal Data:
Answer : A
The essence of Lean is to concentrate effort on removing waste while improving process flow to achieve speed and agility at lower cost.
Answer : A
In order to standardize project savings financial calculation such project benefits can be compared the financial savings are typically calculated over what period of time?
Answer : A