GAQM APM-001 Associate in Project Management APM Exam Practice Test

Page: 1 / 14
Total 704 questions
Question 1

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:



Answer : A


Question 2

After Define Activities and Sequence Activities, the next process is:



Answer : A


Question 3

The correct equation for schedule variance (SV) is earned value:



Answer : A


Question 4

Which of the following is an output of Define Scope?



Answer : A


Question 5

Inputs to the Plan Risk Management process include the:



Answer : A


Question 6

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?



Answer : A


Question 7

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?



Answer : C


Page:    1 / 14   
Total 704 questions