GAQM APM-001 Associate in Project Management APM Exam Practice Test

Page: 1 / 14
Total 704 questions
Question 1

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?



Answer : D


Question 2

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?



Answer : C


Question 3

The cost benefit analysis tool is used for creating:



Answer : B


Question 4

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?



Answer : A


Question 5

Which of the following is a tool or technique used in the Acquire Project Team process?



Answer : C


Question 6

A tool and technique used during the Define Scope process is:



Answer : A


Question 7

The process for performing variance analysis may vary, depending on:



Answer : C


Page:    1 / 14   
Total 704 questions