GAQM APM-001 Associate in Project Management APM Exam Practice Test

Page: 1 / 14
Total 704 questions
Question 1

The probability and impact matrix is primarily used to:



Answer : C


Question 2

At which stage of team development do members begin to work together, adjust work habits, and trust each other?



Answer : C


Question 3

When cost variance is negative and schedule variance is positive, the project is:



Answer : B


Question 4

Which statement correctly describes the value of a business case?



Answer : A


Question 5

Risk responses reflect an organization's perceived balance between:



Answer : A


Question 6

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:



Answer : B


Question 7

Which of the following response strategies are appropriate for negative risks or threats?



Answer : D


Page:    1 / 14   
Total 704 questions