You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.
Answer : B
To determine the charging current for a battery bank, a general rule of thumb is that the charging current should be 5% of the total battery capacity. For a battery rated at 600 Ah, this calculation would be:
600Ah0.05=30Amperes600 \, \text{Ah} \times 0.05 = 30 \, \text{Amperes}600Ah0.05=30Amperes
This ensures the battery is charged efficiently without overloading the rectifier or risking battery damage.
Detailed Explanation:
Battery charging current is typically set as a percentage of the battery's capacity to balance effective charging with longevity and safety. A 5% charging rate is standard for lead-acid batteries, which would be 30 Amperes for a 600 Ah battery bank.
EPI Data Center Specialist References:
EPI standards recommend calculating charging currents based on a percentage of the battery capacity to ensure safety and efficiency, aligning with best practices for battery management in data centers.
When installing a raised floor, can we use a spirit level bar to level the floor?
Answer : B
A spirit level bar should not be used for leveling a raised floor, as measurement errors are likely to propagate from one pedestal to the next. Spirit levels can introduce cumulative errors, leading to uneven floors, particularly in large installations where precise leveling is critical.
Detailed Explanation:
Using a laser level or a precision leveling device is recommended to ensure accuracy across all floor tiles. Spirit levels, while adequate for short spans, can transfer small inaccuracies from one pedestal to another, which can cause alignment issues and floor instability over time.
EPI Data Center Specialist References:
EPI data center guidelines discourage the use of spirit levels for raised floors. Instead, they advocate for precision tools like laser levels that ensure consistency and accuracy in large-scale installations, aligning with best practices for raised floor construction.
What is the calculation for the desired attenuation factor for shielding material?
Answer : C
The attenuation factor for shielding material is typically calculated using the formula A = 20 log (R / M). This equation provides the attenuation in decibels (dB), where R represents the measured electromagnetic field strength, and M is the maximum acceptable level. The logarithmic scale helps quantify how much the shielding reduces EMF levels relative to the maximum allowable value.
Detailed Explanation:
This formula calculates attenuation by comparing the measured value with the acceptable threshold, with the result expressed in decibels. A higher attenuation indicates more effective shielding material, essential for environments requiring robust EMF management.
EPI Data Center Specialist References:
EPI standards include the use of logarithmic formulas to evaluate attenuation levels, ensuring that shielding materials provide adequate reduction in EMF to protect sensitive equipment within data centers.
A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.
The intake temperature is measured at 25 C/77 F and a relative humidity (RH) level of 50%.
The exhaust temperature is 29 C/84 F and 45% RH.
The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.
The pressure under the raised floor is approximately 25 Pa/0.1 inch HO.
Analyze the situation and indicate what the most likely cause is for this server to crash.
Answer : A
The server's repeated overheating despite adequate intake and exhaust temperatures suggests that dust buildup inside the server may be impeding heat transfer. Dust accumulation can obstruct airflow within the server, insulate components, and disrupt the convection-based cooling systems that regulate internal temperatures, leading to overheating and potential hardware failures.
Detailed Explanation:
While the intake and exhaust temperatures appear within acceptable ranges, internal dust can reduce airflow and impede cooling efficiency, causing internal components to overheat despite seemingly normal ambient conditions. Regular cleaning and maintenance are critical for preventing dust-related issues, especially in high-powered equipment like a 5kW server.
EPI Data Center Specialist References:
EPI emphasizes regular maintenance to prevent dust buildup in data center equipment. Dust can significantly impact cooling efficiency and lead to overheating, which underlines the importance of routine cleaning for optimal server performance.
A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.
What type of generators should be installed?
Answer : B
In areas with frequent and extended power outages, continuous generators with at least an N+1 configuration are necessary to ensure consistent power availability. Continuous generators are designed for prolonged operation, making them suitable for scenarios where utility power is frequently unavailable, as in this case with outages exceeding 650 hours per year. An N+1 configuration ensures redundancy, which is critical for maintaining uptime in a high-availability data center.
Detailed Explanation:
Continuous generators provide reliable power over long durations, unlike standby generators, which are intended only for short-term use. The N+1 configuration ensures that there is always an additional generator available in case of failure, thus maintaining power supply even if one generator goes offline.
EPI Data Center Specialist References:
EPI best practices recommend continuous generators with redundancy for data centers located in areas with high power instability to maintain reliability and continuous operation.
A data center has its own power supply from the public utility and receives chilled water supply from the building owner.
What needs to be taken into consideration when calculating the PUE?
Answer : C
When calculating Power Usage Effectiveness (PUE) in a data center that uses chilled water from an external source, like from a building owner, a weight factor for district chilled water must be applied. This is because PUE calculations aim to measure the energy efficiency of the data center's own operations, and external utilities like district chilled water aren't directly powered by the data center. A weight factor of 0.4 is typically used to account for the energy consumed to produce and deliver the chilled water, reflecting the indirect impact on the data center's total energy consumption.
Detailed Explanation:
PUE is calculated as the ratio of the total facility energy to the IT equipment energy. If the cooling is provided by an external chilled water source, it's necessary to adjust the calculations to accurately reflect the energy impact. By incorporating the 0.4 weight factor, data centers can calculate a more accurate PUE, aligning with standard methods and industry best practices.
EPI Data Center Specialist References:
EPI training on PUE highlights the importance of adjusting for external energy sources, such as district cooling, in the calculations. This ensures that PUE values remain accurate and comparable across different data centers, even when external utilities are used.
A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?
Answer : D
For heavy equipment, such as a network storage device weighing approximately 600 kg/1,300 lbs, new floor loading calculations are indeed required, particularly since the rack is non-standard. A structural engineer, approved by the building owner, should conduct these calculations to ensure the floor can safely support the new load without risking structural integrity.
Detailed Explanation:
Data centers are designed with specific floor load ratings, which are determined during the design phase based on anticipated equipment. When adding or replacing equipment that is significantly heavy or non-standard, reassessing the floor's capacity is essential to avoid overloading. A structural engineer has the expertise to verify if the existing floor can accommodate the weight and, if not, can recommend reinforcement measures.
This step ensures compliance with safety standards and helps prevent damage to the infrastructure, which could lead to costly repairs or even catastrophic failure in extreme cases.
EPI Data Center Specialist References:
EPI Data Center Specialist training advises that any changes in the data center load, particularly involving non-standard and heavy equipment, warrant a structural assessment. Ensuring compliance with floor load capacity is a critical safety and operational concern, as underscoring data center infrastructure reliability and safety is a priority in EPI's best practices.