A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.
Which statement is true regarding this scenario?
Answer : B
A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.
What is the most likely reason that the team did not meet the Sprint objectives?
Answer : C
What is an information radiator?
Answer : A
What is a characteristic of a well-designed Agile work space?
Answer : B
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
Answer : B
The team determines that it has over-committed itself for a Sprint.
Who should be present when reviewing and adjusting the Sprint work?
Answer : C
A team is trying to convince a customer about the value of adopting Scrum. The customer likes some of the features of the methodology like the bi-weekly demonstration, but the customer remains largely unconvinced of the value of Scrum and refuses to change the way of working,
What should the team do?
Answer : C