Exin ASF EXIN Agile Scrum Foundation Exam Practice Test

Page: 1 / 14
Total 59 questions
Question 1

Why does the Daily Scrum need to be held at the same location and time?



Answer : B


Question 2

In a Scrum project, when would a requirement get added to the Product backlog?



Answer : C


Question 3

Which means of communication is the most preferable to clarify the interpretation of a requirement?



Answer : B


Question 4

Who should update the work estimates during the Sprint?



Answer : A


Question 5

A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.

Who may best prepare this report?



Answer : B


Question 6

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?



Answer : C


Question 7

What is a Sprint?



Answer : C


Page:    1 / 14   
Total 59 questions