Exin ASF EXIN Agile Scrum Foundation Exam Practice Test

Page: 1 / 14
Total 59 questions
Question 1

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

Which statement is true regarding this scenario?



Answer : B


Question 2

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.

What is the most likely reason that the team did not meet the Sprint objectives?



Answer : C


Question 3

What is an information radiator?



Answer : A


Question 4

What is a characteristic of a well-designed Agile work space?



Answer : B


Question 5

Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?



Answer : B


Question 6

What is meant by the velocity of the team?



Answer : C


Question 7

Which Scrum ritual is meant to look back and improve upon the finished Sprint?



Answer : B


Page:    1 / 14   
Total 59 questions