Question 1

A customer has an existing ACI fabric. Their management has decided to invest in NSX for virtual networking but also retain ACI for their customers and for physical networking.

What is a consideration?



Answer : D

Integrating NSX for virtual networking while retaining ACI for physical networking is possible, but it may be cost prohibitive. This approach requires careful planning and management of both virtual and physical network environments, potentially leading to higher operational costs and complexity.


Technical resources on integrating VMware NSX with Cisco ACI.

Cost considerations and best practices for hybrid network environments.

Question 2
Question 3
Question 4

A customer has a physical server connected to an ACI fabric. The server was recently moved to a different leaf switch within the ACI fabric. The IP address of this server was

also changed but is still part of its original EPG.

What is a consideration once the correct port configuration is pushed from the APIC?



Question 5

What is the standard expected timeline to complete an RCM upgrade?



Answer : D

The standard expected timeline to complete an RCM (Release Certification Matrix) upgrade is 3 weeks. This timeline accounts for the necessary planning, execution, and validation steps to ensure a successful upgrade.


Dell EMC RCM upgrade process documentation.

Best practices for system upgrades.

Question 6

What VMs are part of VxBlock Central?



Question 7

In which cluster does the NSX Controller reside on a VxBlock system?



Answer : A

In a VxBlock system, the NSX Controller resides in the Management cluster. The Management cluster is responsible for housing management components and services, ensuring centralized control and management of the NSX environment.


Dell EMC VxBlock system documentation.

VMware NSX deployment and architecture guides.