CompTIA PK0-005 CompTIA Project+ Certification Exam Practice Test

Page: 1 / 14
Total 291 questions
Question 1

Which of the following is a characteristic that defines a project?



Answer : D

A project is defined by its temporary nature, having both a specific start and end date. This aligns with CompTIA Project+ and general project management definitions, which emphasize a project's unique and finite duration.


Question 2

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project



Answer : B

Sharing a resource like an API between projects to leverage each project's strengths and reduce duplicated efforts is a risk-sharing strategy. CompTIA Project+ outlines risk-sharing as a way to capitalize on opportunities or mitigate project constraints.


Question 3

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?



Answer : B

A downtime window schedule specifies a timeframe during which systems can be taken offline or changed without affecting business operations. CompTIA Project+ includes this as part of deployment planning to ensure minimal disruption to stakeholders.


Question 4

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?



Answer : A

A risk log or risk register is used to document potential risks to the project, including the loss of team members due to high stress. CompTIA Project+ recommends this log as a tool for identifying and managing risks throughout the project lifecycle.


Question 5

When assigning access, classifying information based on sensitivity is referred to as:



Answer : C

Data security involves classifying information based on sensitivity and ensuring that it is protected accordingly. This approach is key in project management to protect sensitive data, as emphasized by CompTIA Project+.


Question 6

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?



Answer : A

A rollback plan is used when an issue is identified during testing or implementation. It allows the team to revert to the previous state, removing the new package. This aligns with CompTIA Project+ guidance on implementing fallback strategies for risk management.


Question 7

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?



Answer : C

A proposal is a detailed document submitted by vendors outlining how they will meet project requirements. It helps in assessing vendor solutions and suitability, consistent with CompTIA Project+ procurement and vendor management practices.


Page:    1 / 14   
Total 291 questions