CompTIA PK0-005 CompTIA Project+ Certification Exam Practice Test

Page: 1 / 14
Total 299 questions
Question 1

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?



Answer : A

IaaS (Infrastructure as a Service) provides virtualized computing resources, such as storage and servers, necessary for hosting a development environment. According to CompTIA Project+, IaaS is ideal for environments requiring infrastructure control without hardware management.


Question 2

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?



Answer : D

Defining communication channels and access requirements typically occurs in the planning phase, where detailed plans for project management are established. This aligns with CompTIA Project+ standards for comprehensive project planning.


Question 3

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?



Answer : C

The Precedence Diagramming Method (PDM) is used to visually represent tasks, dependencies, and sequencing in a project schedule. This technique is consistent with CompTIA Project+ guidelines for planning and managing project timelines.


Question 4

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?



Answer : B

Evaluating the impact to baselines (such as schedule and budget) helps determine the delay's effect on the project. This aligns with CompTIA Project+ guidance on project control, which emphasizes analyzing impacts before taking corrective actions.


Question 5

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?



Answer : C

Closing contracts involves finalizing any remaining contractual obligations and formally closing out the relationship with the vendor. CompTIA Project+ emphasizes this as part of the project closure phase to ensure all legal and financial aspects are complete.


Question 6

Which of the following is a characteristic that defines a project?



Answer : D

A project is defined by its temporary nature, having both a specific start and end date. This aligns with CompTIA Project+ and general project management definitions, which emphasize a project's unique and finite duration.


Question 7

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?



Answer : C

A proposal is a detailed document submitted by vendors outlining how they will meet project requirements. It helps in assessing vendor solutions and suitability, consistent with CompTIA Project+ procurement and vendor management practices.


Page:    1 / 14   
Total 299 questions