CIPS L6M5 Strategic Programme Leadership Exam Practice Test

Page: 1 / 14
Total 83 questions
Question 1

Which of the following pieces of information is required to create a Bill of Quantities? Select all that apply



Answer : A, C, D

A Bill of Quantities is based on the volume/dimensions and price of the materials. Quality and manufacturer details are typically specified elsewhere.


Question 2

The Royal Institute of Chartered Surveyors and the Royal Institute of British Architects are two founding members of which organisation that creates contracts for the construction industry?



Answer : B

The Joint Contracts Tribunal (JCT) is the organisation with these founding members.


Question 3

Petra is setting up a contract for a new construction project that must be robust with little flexibility. The contract stipulates that the client will bear the risk of unforeseen negative circumstances. Which type of contract is most suitable?



Answer : A

FIDIC contracts are known for their robustness and low flexibility, placing risk on the client.


Question 4

Which of the following statements about NEC contracts are true? Select all that apply



Answer : D, E

NEC contracts are designed to be flexible with various payment options and use simple, present-tense English.


Question 5

Under which style of contract is the client, rather than the construction company, responsible for the design of a building?



Answer : B

In Management Contracting, the client retains responsibility for the design.


Question 6

Jennifer is drafting a contract with a "termination for convenience" clause.

Q: What obligations should be included in this clause? (Select all that apply.)



Answer : A, B, C

A termination for convenience clause outlines the responsibilities when a contract is ended early by mutual agreement (p.135).

Returning advance payments ensures fairness.

Destroying confidential data prevents misuse.

Smooth service transition minimizes disruptions.

A review meeting is not mandatory, so it is incorrect. [P.135]


Question 7

Mustard Ltd contracted Red Ltd for IT services, requiring 98% internet connectivity.

Red Ltd has only achieved 90% connectivity despite multiple meetings.

Mustard Ltd now seeks to terminate the contract.

Q: Can Mustard Ltd terminate the contract?

Answer Options:



Answer : D

Connectivity is listed as a warranty, not a condition (p.125).

Warranty breaches allow for damages but do not permit contract termination.

If it were a 'condition' instead of a warranty, termination would be allowed. [P.125]


Page:    1 / 14   
Total 83 questions