CIPS L4M3 Commercial Contracting Exam Practice Test

Page: 1 / 14
Total 189 questions
Question 1

Which of the following is the most suitable model contract for car lift manufacturing?



Answer : C

IMechE/IET: Institution of Mechanical Engineers/Institution of Engineering and Technology - two separate institutes that issue jointly agreed model forms covering the design, supply and installation of electrical, electronic and mechanical plant including special conditions for the ancillary development of software. Car lifts are mechanical products, so IMechE/IET is the most suitable model contract for this type of product.

FIDIC is a French language acronym for Fdration Internationale Des Ingnieurs-Conseils, which means the international federation of consulting engineers. It was started in 1913 by the trio of France, Belgium and Switzerland. The United Kingdom joined the Federation in 1949. FIDIC is headquartered in Switzerland and now boasts of membership from over 60 different countries. FIDIC published its first contract, titled The Form of contract for works of Civil Engineering construction, in 1957. As the title indicated, this first contract was aimed at the Civil Engineering sector and it soon became known for the colour of its cover, and thus, The Red Book. It has become the tradition that FIDIC contracts are known in popular parlance by the colour of their cover. This first contract by FIDIC was undertaken jointly with the International federation of Building and Public works. FIDIC's concerted effort at achieving broad consultation and acceptance of its contract forms has seen subsequent editions of its contracts being ratified by the International Federation of Asian and Western Pacific Contractors Association, Associated General Contractors of America and the Inter-American Federation of the Construction Industry, Multilateral Development Banks among others. Because of the broad support it enjoys, FIDIC contracts are the foremost contracts in international construction.

The Chartered Institute of Procurement and Supply (CIPS) has some model contracts for IT functions including: supply and installation of computer equipment, support and maintenance of bespoke software, servicing of computer equipment,...

The International Trade Centre (ITC) produces contracts specifically designed for small companies doing international business, covering the sale of goods, distribution, services and joint ventures.


LO 3, AC 3.1

Question 2

A senior buyer is preparing specification for the next purchase. He intends to embed social and environmental criteria that align with his organisation's overarching strategy. Which of the following provides the social and environmental objectives that an organisation pursues?



Answer : D

The organisation should have an overarching strategies or policies which sets out the social and environmental objectives to be pursued via procurement and the supply chain generally. Some of these will be about the specification, but that must be tied in other aspects of the sourcing strategy. These objectives, policies and strategies can be found in corporate social responsibility policy.


LO 2, AC 2.1

Question 3

Which of the following regulates barriers to the trade of goods between Member States of WTO?



Answer : B

- The General Agreement on Tariffs and Trade (GATT) is a legal agreement between many countries, whose overall purpose was to promote international trade by reducing or eliminating trade barriers such as tariffs or quotas. According to its preamble, its purpose was the 'substantial reduction of tariffs and other trade barriers and the elimination of preferences, on a reciprocal and mutually advantageous basis.'

- CISG is the Vienna Convention on Contracts for the International Sale of Goods. This is a voluntary treaty under United Nations Commission on International Trade Law (UNCITRAL). The purpose of the Vienna Convention is to set out a framework for international transactions based on a uniform approach. It establishes substantive rules that regulate the duties and obligations of both parties, including the delivery of goods, contract formation, and remedies for breach of contract.

- The Agreement on Trade-Related Aspects of Intellectual Property Rights (TRIPS) is an international legal agreement between all the member nations of the World Trade Organization (WTO). It sets down minimum standards for the regulation by national governments of many forms of intellectual property (IP) as applied to nationals of other WTO member nations.

- The North American Free Trade Agreement (NAFTA; Spanish: Tratado de Libre Comercio de Amrica del Norte, TLCAN; French: Accord de libre-change nord-amricain, ALNA) is an agreement signed by Canada, Mexico, and the United States, creating a trilateral trade bloc in North America.


LO 1, AC 1.3

Question 4

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of 500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to 1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?



Answer : D

A liquidated damages clause specifies a predetermined amount of money that must be paid as damages for failure to perform under a contract. The amount of the liquidated damages is supposed to be the parties' best estimate at the time they sign the contract of the damages that would be caused by a breach. If a breach occurs and the liquidated damages clause is enforceable, the parties do not calculate the actual damages (i.e., how much money a party actually lost as a result of the breach). Instead, the breaching party pays the predetermined sum provided by the liquidated damages provision.

To be enforceable, a liquidated damages clause should meet the following criteria.

Damages are difficult to estimate. A court will be more likely to enforce a liquidated damages provision if the damages that will be incurred as a result of a breach of the contract are difficult to estimate when the contract is entered into. In certain situations, injuries are easy to prove. For example, if a breach will result in the loss of sales, it is easy to determine the actual damages by calculating lost profits. Others are more difficult, like the harm caused by breach of a confidentiality agreement or theft of trade secrets. To be enforceable, the damages should be either uncertain or difficult to quantify at the time the contract is entered into.

The amount is reasonable and not a penalty. If the amount of the liquidated damages is grossly disproportionate to the actual harm incurred, a court will likely find it is a penalty or punishment and will not enforce the provision. When making this analysis, courts usually consider what was reasonable at the time the contract was entered into as opposed to when the breach occurred. There have been cases, however, where courts will decide the reasonableness of the damage estimate based on the actual harm at the time of the breach.

The scenario is excerpted and edited based on a real world case law. In that case, the court held that GPP was entitled to liquidated damages under all four of the EPC contracts, ruling that the provisions did not amount to unenforceable penalties in each of the contracts.


- CIPS study guide page 158-159

- Liquidated damages in energy projects

- What Is a Liquidated Damages Provision?

LO 3, AC 3.2

Question 5

When should liquidated damages clauses be written into a contract?



Answer : D

Liquidated damages are presented in certain legal contracts as an estimate of otherwise intangible or hard-to-define losses to one of the parties. It is a provision that allows for the payment of a specified sum should one of the parties be in breach of contract.

Liquidated damages are meant as a fair representation of losses in situations where actual damages are difficult to ascertain. In general, liquidated damages are meant to be fair, rather than punitive.

Limitations of Liquidated Damages

It is possible that a liquidated damages clause might not be enforced by the courts. This can occur if the monetary amount of liquidated damages cited in the clause is extraordinarily disproportional to the scope of what was affected by the breached contract.

Such limitations prevent a plaintiff from attempting to claim an unsubstantiated exorbitant amount from a defendant. For instance, a plaintiff might not be able to claim liquidated damages that amount to multiples of its gross revenue if the breach only affected a specific portion of its operations. The concept of liquidated damages is framed around compensation related to some harm and injury to the party rather than a fine imposed on the defendant.

The courts typically require that the parties involved make the most reasonable assessment possible for the liquidated damages clause at the time the contract is signed. This can provide a sense of understanding and reassurance of what is at stake if that aspect of the contract is breached. A liquidated damages clause can also give the parties involved a basis to negotiate from for an out-of-court settlement.


- Liquidated Damages

- CIPS study guide page 158-159

LO 3, AC 3.2

Question 6

Consequences and actions that arise from certain KPI scores must be...? Select TWO that apply.



Answer : A, C

Supplier performance management and monitoring is a fundamental part of contract management. It starts with setting KPIs, targets and consequences or actions that arise from KPI scores. The measures, objectives and targets used in the monitoring of the supplier's performance must reflect those that were agreed when the contract was let. That is why it is important to specify a commitment to continuous improvement at the outset. It would be unfair to the supplier to suddenly introduce a range of measures after the contract had begun - however if such an introduction mid-term through the contract is unavoidable then it should be negotiated and agreed in a professional manner and not merely imposed on the supplier.

In conclusion, the details of how KPIs will be monitored and the actions or consequences resulting from scores achieved must be documented and agreed between the parties. This details may be embedded in the specification or the main body of the contract or it may be set out in a SLA.


- Performance Monitoring of Suppliers - CIPS Knowledge summary

- CIPS study guide page 101-109

LO 2, AC 2.2

Question 7

Which of the following statement is true about insurance?



Answer : A

An insurance policy transfers a risk from one party to another in exchange for payment, it does not transfer the liabilities from the insured to insurer.

Insurance policies are taken out as a form of protection against a specific risk or unfortunate occurrence. If one party indemnifies another to protect that other party in the event of a risk occurring then the indemnity itself is merely a statement of intent. There also need to be some mechanism of substance to back up that indemnity. This BACK UP is the insurance policy which can be relied upon to meet the indemnity being given. In fact, most indemnity provisions are backed up by insurance coverage.

Professional indemnity or liability insurance offers such coverage to professional advice or service providing individuals and companies ensuring protection against any legal costs and damages awarded as a result of claims relating to negligence. Whereas more general forms of liability insurance focus on direct forms of harm such as sustaining injuries, professional indemnity insurance provides a far more detailed and comprehensive form of coverage. The cover protects a firm or individual's liability relating to any financial loss caused by errors or omissions in the service provided as well as any alleged failure to perform on behalf of a client.

Goods in transit insurance does what it says on the tin, protecting any goods your business delivers or transports from place to place. The responsibility to pay the insurance premium is negotiable, it may belong to the supplier or the buyer.


- Is that Covered? Insurance and Indemnity Clauses

- Professional Indemnity Insurance

- Goods in transit insurance

- CIPS study guide page 150-153

LO 3, AC 3.2

Page:    1 / 14   
Total 189 questions