Certinia PSA-Sysadmin PSA System Administrator 2023 Exam Practice Test

Page: 1 / 14
Total 60 questions
Question 1

What tool can be used to "schedule backlog calculation" and "schedule utilization calculation" in PSA?



Answer : B


Question 2

Where would you go to opt in for push updates, or to update the schedule of when an update will be pushed for FinancialForce applications?



Answer : C


Question 3

A Project Manager wants to generate a report on the Project's Margin, Revenue, and Costs for a specific period, and to be able to reuse it.

How do you set up this requirement in the Org?



Answer : B


Question 4

The consultants in your organization will be entering time against the project task and everyone else will enter time against the project/milestone.

Which of the following correctly identifies the steps you will need to complete?



Answer : B


Question 5

A user is having an issue where the Utilization report has inflated hours. The billable hours, calendar hours, and credited hours are double their actual values.

Which of the following is a possible cause of this issue?



Answer : C


Question 6

Currently Project Managers and Resource Managers are using Gantt. You do not want your Project Managers creating assignment, resource requests or milestones from the Gantt. Which of the following custom settings should you configure to hide these buttons?



Answer : B


Question 7

Your company is rolling out Skills and Certifications to encourage employees to track their skills and also decide which skills they would like to acquire. After rolling this feature out, end-users have noted they can't add their assignments to build their "Experience". What could be causing this problem?



Answer : C


Page:    1 / 14   
Total 60 questions