Blue Prism ASD01 Designing Blue Prism Process Solutions Exam Practice Test

Page: 1 / 14
Total 27 questions
Question 1

Which of the following statements about using Work Queue designs to split a business process into a multi part robotic solution is correct?

1. Using multiple Work Queues and Processes for the different stages of the business process is a valid design option to split a business process into a multi part robotic solution

2 Using a single Work Queue and deferring cases for future processing is a valid design option to split a business process into a multi part robotic solution

3. Using an item's status to control when to work it is a valid design option to split a business process into a multi part robotic solution

4. You cannot split a business process into a mufti part robotic solution



Answer : D


Question 2

The status of a Work Queue can be used as a method of recording what work has been done so far on a Work Queue item

Please consider the following statements:

1. For Ml, to easily see how far an item has been worked

2 To aid manual working of exceptions, providing the Item Status can inform staff what work is still outstanding on an item that needs manually completing

3. To enable Work Queue items to be safely retried, a process can use the item status to know which updates have already been performed so that they are not repeated

4 To record the Customer's Surname

Which of the statements are valid reasons for updating a case status?



Answer : C


Question 3

A process definition document has been produced for a process that interfaces with two applications FirstApp and Customer Information (CI) The

process requirement is to perform data extraction from FirstApp before performing a number of steps in the CI application.

It is estimated that to perform the daily case volume within SLA's will require 10 robots Average license time is approximately 10 minutes, with the

FirstApp steps requiring only 1 minute to perform.

The client has a limited number of licences for the FirstApp application and is reluctant to use 10 of these licenses to automate the process.

Which of the below is a valid design option for the project?



Answer : A


Question 4

Which of the following statement combinations about Blue Prism memory management is correct?



Answer : A


Question 5

Which of the following statements about Blue Prism and Web Services is correct?



Answer : D


Question 6

Which of the following accurately describes best practice when work is sourced from an application's workflow system?



Answer : A


Question 7

A retail bank has promoted 2 Blue Prism processes to production

1. Email poller

2 Customer onboarding

3. Direct Debit Cancellations

One instance of the email poller process will run 24/7 feeding work queues for the other two processes.

Three instances of the Customer onboarding process will run between 6am and 11 pm each day on three separate VMs

One instance of the Direct Debit Cancellations process will run between 6am and 4pm each day on the same VM as the Email poller process

What is the maximum number of Blue Prism licenses that will be consumed each day?



Answer : A


Page:    1 / 14   
Total 27 questions