APMG-International Better-Business-Cases-Practitioner Better Business Cases Practitioner Exam Practice Test

Page: 1 / 14
Total 96 questions
Question 1

Providing better facilities, improving learning provision and offering a wider choice of education courses.

Which of the key objectives for spend are these objectives based on?



Answer : C


Question 2

An extract of an entry in the benefits register includes the following information:

1. Benefit type: Cash-releasing

2. Description: A net overall saving in the cost of cleaning

3. Target improvement: Reduce overall costs of cleaning contracts by 10% per annum

4. Responsible officer: Pittville University Procurement Manager.

Which 2 statements apply to these entries?



Answer : B, D


Question 3

The current establishment of support staff will be able to absorb 30% growth in numbers of 16 - 18-year-old learners.

This information has been:

1. Entered in the benefits register

2. Classed as a cash-releasing benefit.

Which 2 statements apply to these entries?



Answer : B, C


Question 4

The Management Case states that, because the Pittville project is part of the Western Area Learning Improvements Programme:

1. A benefits realization strategy and benefits register are NOT required for the project.

2. All benefits will be tracked at the programme level.

Which 2 statements apply to these entries?



Answer : A, B


Question 5

The benefits realization strategy states that the following:

1. Benefits will be entered in the benefits register

2. Only cash-releasing benefits will be tracked in the benefits register.

Which 2 statements apply to these entries?



Answer : B, C


Question 6

It is estimated that 60% of the taxation costs on the development will NOT be reclaimable.

Should the unclaimable taxation costs be excluded from the Financial Appraisal?



Answer : B


Question 7

The new campus scheme will take three years to complete. Projected inflation over this period will mean that staffing costs will be 6%

higher when the campus is operational.

Should this increase be managed as a risk to the project?



Answer : C


Page:    1 / 14   
Total 96 questions