Which of the following is NOT true?
Answer : A
Why does activity 11001 not show successor activities?
Answer : D
In a "crashed" schedule, which is a chain of activities that precede activity 2004?
Answer : A
What is the workweek period for this project?
Answer : D
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
Answer : A
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
Answer : D
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
Answer : B