AACE International AACE-PSP Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 163 questions
Question 1

What changes to logic would eliminate Activity B from the critical path?



Answer : D


Question 2

What day would Activity C complete if the duration of Activity B was reduced to zero?



Answer : C


Question 3

What day would Activity C complete if the duration of Activity A was reduced by five days?



Answer : B


Question 4

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?



Answer : C


Question 5

Using the normal schedule, what is the early finish date and total float of Activity 10002?



Answer : D


Question 6

Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?



Answer : A


Question 7

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?



Answer : A


Page:    1 / 14   
Total 163 questions