AACE International Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 120 questions
Question 1

Which of the following is NOT true?



Answer : A


Question 2

Why does activity 11001 not show successor activities?



Answer : D


Question 3

In a "crashed" schedule, which is a chain of activities that precede activity 2004?



Answer : A


Question 4

What is the workweek period for this project?



Answer : D


Question 5

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:



Answer : A


Question 6

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?



Answer : D


Question 7

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?



Answer : B


Page:    1 / 14   
Total 120 questions