What changes to logic would eliminate Activity B from the critical path?
Answer : D
What day would Activity C complete if the duration of Activity B was reduced to zero?
Answer : C
What day would Activity C complete if the duration of Activity A was reduced by five days?
Answer : B
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
Answer : C
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Answer : D
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Answer : A
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Answer : A