AACE International Planning & Scheduling Professional (PSP) Exam Practice Test

Page: 1 / 14
Total 120 questions
Question 1

What is the free float for Activity F?



Answer : B


Question 2

Which activity is drawn in the incorrect position?



Answer : D


Question 3

What is the actual duration as of the status date or data date of Activity B?



Answer : B


Question 4

What does the narrow band at "Y" represent?



Answer : D


Question 5

What is the relationship depicted between Activity G and Activity H?



Answer : B


Question 6

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?



Answer : A


Question 7

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?



Answer : C


Page:    1 / 14   
Total 120 questions